Site Review Scores

Saturday, June 28, 2025

Michigan NEVI Funding Round 2 Site Analysis

 On June 17, 2025, MDOT released the list of Round 2 NEVI funded Design-Build-Operate-Maintain (DBOM) award winners.  The list shows the node, address, highway corridor, the company selected to get the award and the amount of money given out for each site.  This improves on the data released with round 1 where I had to guess the site locations, so I don’t have to list my confidence level.  As the round 1 builds start to pick up, we now have 48 new sites to track.  Look to the end of this report of a summary and highlights of the money being spent.

The full MDOT release list can be found here: 

MDOT NEVI Round 2


My Round 1 Award Analysis and Tracking can be found here:

MI NEVI Round 1 Analysis

Upper Peninsula (UP) sites [only 2 new sites awarded]:

Sites in Michigan’s UP have the challenge of the lack of high-power infrastructure, so any site here will either need to be supported by a battery backup or will likely end up having almost cost prohibitive charging.

Quinnesec:

Expanding on their Round 1 awards, eCAMION USA, Inc.(DBA Jule) was selected for the site at 3851 Menominee St, Quinnesec, MI 49876, right on the US-2 AFC.  I expect the standard 440kWh of on-site battery storage and then the required 4 – 150kW dispensers.  The site should have both CCS1 and J3400 connectors at each dispenser.  The site here should look like the Jule site in Port Huron or Cedar River but upgraded to meet the 600kW total output NEVI requirements.

St. Ignace:

Universal EV LLC is a new award winner in Michigan, but they have multiple NEVI and other state funding awards, mostly focused on the mid-west.  I have not been impressed with their service, ability to build out, nor the reliability of their selected hardware partner.  Typically, Universal EV has used ChargeTronix hardware, but I have seen a lot of problems keeping this hardware working.  The site here is at 680 US-2, St Ignace, Michigan 49781 and likely to be hosted by Cedar Hill Lodge.

Lower Peninsula sites:

Looks like there were 2 primary focus point in the 2nd round.  First, there are many new sites in the metro Detroit area.  This should allow for sites to be installed where usage is likely to be high.  Second, there were some gaps in the AFC from round 1 that got filled.  For these sites, I am going to group them by award winner so that the hardware details can be listed once and then the site details for each location can be summarized.

Universal EV LLC made a decent entry with multiple site selections.  Typically, Universal EV has used ChargeTronix hardware.  Universal EV primarily partners with hotel properties for install locations and this is confirmed by the site list.  If they are as slow in Michigan as they are in other locations, don’t expect to see any of these sites before 2027 at the earliest.


Pellston Lodge: 1600 US-31, Pellston, MI 49769

Country Inn & Suites: 2260 James St, Holland, MI 49424

Best Western Plus: 630 E Chicago St, Coldwater, MI 49036

Super 9 Inn: 400 B-Drive N, Albion, MI 49224 

Super 8: 3933 S Lotz Rd, Canton, MI 48188

Marathon Gas: 377 S Schaefer Hwy, Detroit, MI 48217

In addition to the one new UP site, eCAMION USA, Inc.(DBA Jule) was selected for 3 other sites.  We can expect to see more of their custom battery backed solutions at these new sites.  Jule tends to partner with local government locations/offices based on the lower traffic areas they choose to support.


Hometown Inn: 4375 Brudy Rd, Indian River, MI 49749

Elk Rapids Government Center: 315 Bridge St, Elk Rapids, MI 49629

Mobil Gas Station: 2524 M-52, Webberville, MI 48892


In round 2 Francis Energy has been selected for 2 sites.  Francis Energy is a fast-growing Charge Point Operator (CPO) based in Oklahoma.  They have NEVI sites operational in Ohio, Pennsylvania, Colorado, New Mexico and Texas.  Francis Energy has a contract with SK Signet for 1000 units.  This hardware has already started to be installed at the Francis Energy NEVI sites.  Francis Energy has shown that the NEVI sites have held high prices.


Family Fare Supermarket: 111 M-66, Charlevoix, MI 49720

Taco Bell: 1433 E Grand River Ave, Portland, MI 48875


Red E Charging is back with another strong showing in their home state with 13 additional site selections.  They have already started construction on partner NEVI round 1 sites.  They continue to build the relationship with their preferred hardware partner Autel, and we can expect more of this hardware for Round 2 sites.  Red E Charging has built many strong relationships with gas station owners, and this is the focus.


Wesco: 21380 Perry Ave, Big Rapids, MI 49307

Wesco: 6419 Airline Rd, Fruitport, MI 49415

Shell: 6380 Blue Star Hwy. Saugatuck, MI 49453 – New site or upgrade existing across the street

Shell: 469 Broadway, South Haven, MI 49090

Shell: 61828 CR 687, Hartford, MI 49057

Sunoco: 35777 S Huron Rd, New Boston, MI 48164

Shell: 9999 Middlebelt Rd, Romulus, MI 48174 – Airport Hub

BP: 26727 Southfield Rd, Lathrup Village, MI 48076 – Upgrade existing site

Beyond Juice: 21110 Mack Ave, Grosse Pointe Woods, MI 48236 – Upgrade existing site

Wesco: 3090 Colby Rd. Whitehall, MI 49461

Shell: 2679 Ann Arbor-Saline Rd, Ann Arbor, MI 48103

BP: 25700 Dequindre Rd, Warren, MI 48091

Sunoco: 645 Mennard Dr. Lansing, MI 48917


GPM Southeast have expanded on their Round 1 site selections with 7 additional Round 2 sites.  The site host of choice are the gas station properties.  Since the initial analysis, I have known that for these sites, the CPO partner is Red E Charging.  With this partnership, we can expect Autel Maxi-charge hardware at these locations.


Shell: 125 68th Ave S, Coopersville, MI 49404

Marathon: 12160 W Olive Rd, Grand Haven, MI 49417

Marathon: 5658 W Main St, Kalamazoo, MI 49009 

Marathon: 1149 M-89, Plainwell, MI 49080 – Upgrade existing site

Marathon: 4315 Chicago Dr SW, Grandville, MI 49418

BP: 8830 Main St, Birch Run, MI 48415 – Upgrade existing site

BP: 520 E Pinconning Rd, Pinconning, MI 48650


EVgo has been selected to add to the 2 sites awarded in Round 1 with 2 more sites in Round 2.  The locations listed in the selection are interesting in that both are next to partner Meijer locations that currently have other charging options.  We can expect that EVgo will continue to delivery their partner Delta hardware, no matter where these sites end up.


Goodwill: 2700 Kraft Ave SE, Grand Rapids, MI 49546 - Adjacent Meijer has ChargePoint units

Kohl's: 20155 Haggerty Rd, Northville, MI 48167 – Adjacent Meijer that has now abandoned? Shell chargers


Tesla has a huge network and has been selected for 3 sites in Round 2.  One new site is already on the Tesla roadmap as coming soon, one is a site upgrade, and one is near the Tesla store location.  We can expect probably 12 stall Supercharger installations at each of these sites.


Family Fare Supermarket: 847 S Kalamazoo St, Paw Paw, MI 49079

Meijer: 2980 E Wilder Rd, Bay City, MI 48706 – Existing V2 site to be upgraded

Oakland Mall: 412 W 14 Mile Rd, Troy, MI 48083 – Site of the Michigan Tesla store


Love's Travel Stops follows up their 2 sites awarded in Round 1 with 2 more sites in Round 2.  Additional Love’s Travel Stops will be getting fast charging installations based on these awards.  Based on the NEVI sites open in PA, we can expect ChargePoint Express Plus hardware under a nice canopy.


Loves Travel Stop: 18720 Partello Road, Marshall, MI, 49068

Loves Travel Stop: 7300 West Grand River Ave, Grande Ledge, MI, 48837


Quality Dairy Company is a new entrant for Round 2.  They were selected for 1 site, at a company store in Charlotte, MI.  Not 100% confident on the hardware/CPO partner, but I am guessing for now that it will be Red E Charging and their Autel hardware.


Quality Dairy Store: 680 Lansing Rd, Charlotte, MI 48813


Safiedine Oil Co. is another new entrant for Round 2.  They have 2 site selections at company owned gas stations.  Not 100% confident on the hardware/CPO partner, but I am guessing for now that it will be Red E Charging and their Autel hardware.


Exxon: 24000 Plymouth Rd, Redford, MI 48239

Exxon: 46963 Gratiot Ave, Chesterfield, MI 48047


Ford Road Petro Real Estate is also new for Round 2.  They were selected for single site at a Mobil gas station.  Not 100% confident on the hardware/CPO partner, but I am guessing for now that it will be Red E Charging and their Autel hardware.


Mobil: 10000 Ford Rd, Dearborn, MI 48126


Pilot Travel Centers expands on their NEVI awards (3 in Round 1) with an additional 3 selections in Round 2.  I expect that this will continue to follow the existing pattern of partnering with EVgo.  One of these is a very low cost, but that is because the site already exists, so this money may only be used to support data reporting and other NEVI requirements.


Pilot Travel Center: 21055 West Rd, Woodhaven, MI 48183

Pilot Travel Center: 2424 Wadhams Rd, Kimball, MI 48074 - Upgrade existing site

Pilot Travel Center: 195 Baker Rd, Dexter, MI 48130


Electrify America joins the crowd of Round 2 site selections.  They received a selection to upgrade the existing site in Cadillac, MI to NEVI compliant hardware and software.  We can look forward to them completing a upgrade to this site including new BTC Power hardware with dynamic power sharing between the 4 dispensers.


Meijer: 8605 34 Rd, Cadillac, MI 49601 - Existing site upgrade


Thanks for taking the time to read through this initial analysis.  Look forward to some analysis videos highlighting these potential new sites.

Money Summary:

In this second round of funding MDOT has selected about $24.5 million dollars in awards.  For 48 sites, this comes in at just over $500k per site average, which compares to the Round 1 site average of $550k per site, down just slightly.  The most expensive award, once again, goes to Francis Energy for $1.07 million towards the site in Charlevoix.  The least expensive is only $41k to Pilot Travel Centers for an existing site in Kimball.  As far as numbers of sites goes, Red E Charging continues to lead with their additional 13 sites, with GPM Southeast and Universal EV sharing second with 7 awards each.

50 Mile Radius Loops

25 Mile Radius Loops

The Detroit coverage is so dense that 5 mile radius loops were needed to reduce the overlap on 13 new sites:




Wednesday, April 16, 2025

Michigan Charging Site Preview Part 1

 Until there is time for some new site reviews, here is a preview of some of the charging infrastructure that is coming soon in Michigan.



Tuesday, April 1, 2025

One North Kitchen and Bar – Jackson

Introduction

This is a site review from my trip to cover updates to the I-94 east/west corridor.  Site visits on November 8, 2024.

Business/Location Name

One North Kitchen and Bar

Address

2115 Bondsteel Dr, Jackson, MI 49202

Network

Red E Charge

Station Details

One 180kW Dual Port EVSE

Cost

$0.50/kWh


The One North Kitchen and Bar in Jackson, MI station was the 11th and final charging stop on my trip to check out added charging options along the I-94 corridor. North of I-94 one exit along US-127.  (This station opened in August 2024).  




Accessibility

This station placed on the corner of the parking lot for this restuant.  Located 0.3 miles from US-127 exit 44, and just 1.1 miles from I-94 exit 138.  The spots are marked for EV charging only, but in this busy lot could easily be blocked.  Parking spaces are tight giving little room to maneuver for non-optimal charge port locations.  No pull thru options here for anyone pulling a trailer.



Amenities

Very limited amenities at this site.


Dining options include: One North Kitchen and Bar, Yen King

Shopping options include: None

Car-related services (windshield cleaning, air):  None


Concentration

This is a single Red E Charge Autel MaxiCharger capable of outputting power to both connectors at the same time.  This station is the pull/back into configuration, easy charging with Elektra’s front port location or when backing in with Voltron to charge.  Using this spot in a busy restaurant parking lot does limit the expansion, and I could see these spots being blocked often.



Location

I am happy to see that the Detroit based Red E Charge continues to invest in charging throughout the state.  This site supports the middle of MI in the I-94 corridor.  At about 80 miles to Detroit and 140 miles to New Buffalo, this site offers a good intermediate stop option.

50 Mile Radius:


150 to 200 Mile Range Estimate:


Speed

This Autel MaxiCharger is a step up from the ChargePoint CPE 250 units populated for destination charging. The rated 180kW is achieved by using the air-cooled cables in boost mode to provide up to 400 A for short periods of time to match the charging curves of many vehicles.  Higher voltage vehicles should be able to take advantage of the output power from these units.  My car slowly stepped up to the 180kW max before settling back to a 200A output for most of the charge.  The onsite 500 kVA transformer supports this unit and could support an expansion to one more in the future.



    

Summary

Built for expansion, it is good to see electric vehicle mobility supported by continually expanding infrastructure.  This site is on par with many of the other Red E Charge sites I reviewed this year. I will note that when I visited this site my first attempt to charge timed out due to me starting the charge too soon.  The second attempt failed due to some network error.  I called Red E Charge and the person on the other end reset the unit and walked through the process to make sure I was able to get charging successfully.  They were even able to help me when I did not have record of how long the session was.  I called them and based on the details of my charge session, they were able to tell me that I charged for 18 minutes.  Overall an excellent trip and mostly positive charging experiences.


What I paid for this stop: 

Total Cost: $20.96

Total kWh: 41.92

Time: 18 minutes

Average Charge Speed: 140 kW (calculated)

Cost per kWh: $0.50




Total Score (Max 44)

Score

Accessibility

Amenities

Usability

20

C

3

1

16


Questions or Comments:

dantheevman@gmail.com


Friday, March 21, 2025

4 Year Anniversary

 4 years, 132 posts, over 100 site visits/reviews.

Not sure what I expected 4 years ago when I started this journey, but I have sure have covered the road trips, charging site reviews, and even a little bit of in depth EV Charging News.

Since I started with Elektra, she is still going strong putting in excellent commuter duty and putting up with Michigan winters remarkably well. 

Those that have followed know that Voltron is also now part of the fleet and he continues to shine in the road trip roll.

Looking ahead to the next 4 years, I hope that the charging infrastructure will continue to grow and I will have an equal number of new sites to visit and review.  I have already started some video news content and the site reviews may go video in the future.

Thank you to all that have checked the site over the last 4 years, and I hope to keep providing valuable content for years to come.

Wednesday, March 19, 2025

Marathon – Plainwell

Introduction

This is a site review from my trip to cover updates to the I-94 east/west corridor.  Site visits on November 8, 2024.


Business/Location Name

Marathon/Admiral

Address

1149 M-89, Plainwell, MI 49080

Network

Red E Charge

Station Details

One 160kW Dual Port EVSE

Cost

$0.50/kWh + $0.50 Session fee


The Marathon/Admiral in Plainwell, MI station was the 10th charging stop on my trip to check out added charging options along the I-94 corridor. This gas station just off the highway makes for a decent travel stop.  (This station opened in April 2024).  




Accessibility

This station is placed in the back corner of the parking lot for this convenience store.  Located 0.1 miles from US-131 exit 49, this gas station is at the northwest corner of the intersection with M-89.  The spots are marked for EV charging only.  No pull thru options here for anyone pulling a trailer, but parking spaces are wide enough to enable this if only one vehicle charging.



Amenities

Very limited amenities at this site.


Dining options include: Starbucks, Wendy’s, Burger King, McDonald’s

Shopping options include: None

Car-related services (windshield cleaning, air):  Marathon gas station at this location


Concentration

This is a single Red E Charge Autel MaxiCharger capable of outputting power to both connectors at the same time.  This station is the pull/back into configuration, easy charging with Elektra’s front port location or when backing in with Voltron to charge.  The number of stations here matches the expected need for supporting travel on this route.



Location

I am happy to see that the Detroit based Red E Charge continues to invest in charging throughout the state.  This site supports the west site of MI in the Douglas area.  At about 195 miles to Detroit and 145 miles to Chicago, this offers a coastal stop


50 Mile Radius:



150 to 200 Mile Range Estimate:



Speed

This Autel MaxiCharger is a step up from the ChargePoint CPE 250 units populated for destination charging. The rated 180kW is achieved by using the air-cooled cables in boost mode to provide up to 400 A for short periods of time to match the charging curves of many vehicles.  Higher voltage vehicles should be able to take advantage of the output power from these units.  The onsite 300 kVA transformer supports this unit and could support an expansion to one more in the future.



    

Summary

Built for expansion, it is good to see electric vehicle mobility supported by continually expanding infrastructure.  This site is on par with many of the other Red E Charge sites I reviewed this year. I was amused because at the time of my visit the gas pumps at this gas station were all marked off and non-functional.  I would have been able to ‘gas’ up at this location, but normal gas cars would not have been able to do the same.


I didn’t charge at this location, having just charged up at the previous site and planning to charge at the next.


What I paid for this stop: (I did not charge at this site)

Total Cost: 

Total kWh: 

Time: 

Average Charge Speed: 

Cost per kWh: 




Total Score (Max 44)

Score

Accessibility

Amenities

Usability

24C6513

Questions or Comments:

dantheevman@gmail.com


Videos

I made a video

  I have seen a couple of series following other CPO build outs.  I thought I would try my hand at providing some insight and commentary.  T...